6/29/11 – Contract executed with WorkForce Software for EmpCenter product.

6/22/11 – Project Implementation Team kickoff meeting.

6/23/11 – Project Steering Committee kickoff meeting.

6/29/11 – Stakeholder Committee kickoff meeting.

7/22/11 – WorkForce project kickoff meeting.

8/1/11 – Core Concept training.

8/22-8/30/11 – Payroll/HR process review meetings.

9/15/11 - Steering Committee Meeting.

9/26-9/30/11– Requirements gathering sessions with WorkForce and various campus subject matter experts.

10/20/11 - Steering Committee Meeting.

10/24-10/28/11 – Requirements gathering sessions with WorkForce and various campus subject matter experts.

11/7/11 - Classified Staff Focus Group.

11/11/11 - Unclassified Staff Focus Group.

11/11/11 - Review of results from requirements gathering sessions, core group.

11/14/11 - Student Employees Focus Group.

11/15/11 - Supervisors Focus Group.

11/17/11 - Steering Committee Meeting.

1/17/12 - Requirements documents review work meeting with core group.

1/18/12 - Steering Committee Meeting.

1/27/12 - Testing Prep Training.

4/27/12 - Mid-Configuration Demo.

 