Authorization to proceed with solicitation or execution of a contract to a consulting or construction firm must come in writing from Facilities Services or authorized departmental project and/or construction manager. After authorization has been received by Facilities Services all submissions for construction or consultant solicitations or contracts shall be submitted to the Construction Contracts Supervisor in PaCS.
PROCEDURE:
a) Design requests: Facilities Services or authorized departmental project manager or construction manager must send an email to the Construction Contracts Supervisor, including the following:
- Name of OSU project manager
- Index or Facilities Services work request number
- Description of project, estimated project budget, and authorization for expenditure of funds for design
- Design proposal containing the following:
- Name, address, phone and email for design firm’s project manager
- Description of project and services to be provided
- Not-to-exceed fee for services and separate reimbursable expenses
- List of personnel to be assigned to the project.
b) Construction requests: Facilities Services or authorized departmental project manager or construction manager must send an email to the Construction Contracts Supervisor, including the following:
- Name of OSU project & construction managers
- Index or Facilities Services work request number
- Description of project, construction estimate, and authorization for expenditure of funds for construction
- Desired method of procurement
- Hard copies of drawings, one-sided set of specifications and review comment responses from the design consultant, if applicable.